1. List all the tasks that are on the critical path. 2. Find the total tim

 
Get Writing Help
 

1.
List all the tasks that are on the critical path.
2.
Find the total time to complete the project (In
days)
3.
What is the slack or float of task “D”?
4.
If you increased Task D’s duration from 4 days to 5
days, what effect will this have on the project?
Please use the picture attached to answer the questions.

 